EKFB works notices – A413 London Road and Rocky Lane
Please find attached the advanced works notices for works due to take place in May and June on the A413 London Road and Rocky Lane.
The construction of our conveyor over the Chiltern Rail line at Easter went well so the focus now is to continue the installation over the A413 London Road and connect power. The construction of the conveyor will complete in the summer and will prevent us from having to transport excavated materials on the A413 in HGVs.
The works you can expect to see over the next few weeks is as follows:
- Short duration closure of Small Dean Lane to pedestrians, cyclists and those on horseback on 10th & 11th May for the conveyor installation over the road.
- Continuation of the lane closure on London Road on weekdays until 27th May.
- Full overnight closures on London Road on 18th and 19th May and 14th – 16th June, the road will be open during the day.
- Full closure of Rocky Lane from 23rd May to 10th June
- Lane closure on London Road between the petrol station and Rocky Lane from 30th May to 10th June.
The purpose of these lane and road closures are contained in the attached works notices. These dates are subject to alteration should we encounter delays to our works for reasons beyond our control.
We apologise for the inconvenience and we will work to get the roads and lane open again as soon as possible.
Notice of Road Closure Rocky Lane _ May 2022
Notice of road closure update A413 London Road May 2022 (003)