HS2 Works Notification: Abnormal load deliveries, Aylesbury
We’re writing to let you know about some planned works that we will be carrying out in your area.
Throughout 2023, our teams will be moving into our main construction phases for the various bridges and the viaduct that will be built in the Aylesbury area.
We will soon begin receiving deliveries of precast concrete beams. Some of these beams will be 30m in length and therefore will be classed as abnormal loads.
In early 2023, we will be starting to work on the A41 overbridge. In order to get the right supplies to the site we will require over 20 abnormal load deliveries to build the overbridge.
The delivery of the A41 overbridge is due to take place over a three-week period commencing on the 30 January 2023 off peak from 8pm. However, due to the number of abnormal loads required for this build, we may be receiving deliveries of this size for the next few months.
These dates may change due to conditions outside of our control. Please refer to the HS2 website regularly to check for any changes and updates.
Wherever possible, we will minimise the impact on highway users by coordinating deliveries to avoid peak times.
Please see details of the works here:
Our work is subject to change – for live traffic information go-to one.network and please check on-the-road signs.
- Use our in your area map to search current and planned HS2 works, developments and opportunities in your area.
- Visit your local community webpages to find information about HS2 works and developments in your area.
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk.