HS2 Works Notification: upcoming Network Rail possession

We’re writing to let you know about some planned works that we will be carrying out in your area.

As part of the Small Dean Viaduct construction works, we will be realigning a section of the A413 London Road early next year. During November in preparation, works will take place adjacent to the road to prepare the area for utility diversions in December, this will require over road closures for a week.

The works will involve creating a crossing point to enable our site vehicles to safely cross the A413 London Road as well as erecting perimeter fencing. These works can only take place whilst the rail line is closed which we are currently only permitted to do on Saturday nights.

The rail line closure will be implemented after the last train service of the day so that train services should be unaffected however, please check with the train operator before travelling.

In late November we will introduce temporary traffic lights on the A413 London Road to enable concrete lorries to turn right from our compound to get to our Nash Lee batching plant. The reason for this is to enable us to complete a large concrete pour for the Wendover Dean Viaduct.

A section of the A413 London Road will be fully closed overnight from 8pm – 6am on Monday 28th November to Friday 2nd December.
We will also be closing the A413 London Road between 9pm – 6am on Saturday nights on the following dates:

  • 26th November
    • 3rd December
    • 10th December
    • 17th December

These dates may be subject to change due to circumstances outside of our control. In the event that our works are completed early, some of these closures may be shorter than advised.

 

Please see details of the works here:

 

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk.