HS2 Works Notification: Wendover and Quainton temporary traffic management
We’re writing to let you know about some planned works that we will be carrying out in your area.
Wendover – Traffic management, A413 Wendover
In preparation for the main construction works of the Small Dean Viaduct we will have temporary traffic management on a section of the A413 London Road, between the Small Dean roundabout and Rocky Lane.
There will be traffic management in the form of a lane closure and two-way traffic lights, 9.00am to 3.00pm, from Monday 15 August to Friday 2 September 2022. These dates may be subject to change due to circumstances outside of our control, such as weather.
Please see details of these works here:
- Utility relocation and connections on Station Road and Fiddlers Field, also known as Snakes Lane;
- Site access construction on Station Road; and
- There will also be times where multi-phase traffic lights will be used on a section of Fiddlers Field and the junction on Station Road.
When will these works take place?
- Phase 1 – Station Road North – Thursday 14 July to Friday 22 July – completed.
- Phase 2 – Station Road South – Monday 25 July to Thursday 12 August (24/7)
- Phase 3 – Fiddlers Field – Saturday 13 August and Sunday 14 August (24/7)
- Phase 4 – Fiddlers Field/Lee Road – Monday 15 August and Tuesday 16 August (24/7)
- Phase 5 – Station Road North– Wednesday 17 August to Friday 30 September (24/7)
Please see details of these works here:
- Visit your local community webpages to find information about HS2 works, developments and opportunities in your area.
- Use our In your area map to search current and planned HS2 works and developments in your area.
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk.