Week Eleven of Manor Waste Refurbishment

This week work will continue on cable ducting, La Linia paving and bollards, all in the War Memorial area.

To read about the survey completed prior to this work, clickhere

To see some videos of work in progress clickhere

To see what happened in week one, clickhere

To see what happened in week two, clickhere

To see what happened in week three, clickhere

To see what happened in week four, clickhere

To see what happened in week five, clickhere

To see what happened in week six, clickhere

To see what happened in week seven, clickhere

To see what happened in week eight, clickhere

To see what happened in week nine, clickhere

To see what happened in week ten, clickhere

  • Monday 4 April:Wendover Hardware and Lloyds Pharmacy are only accessible from Back Lane.
  • Tuesday 5 April:Levelling in preparation for the slabs in front of Lloyds Pharmacy
  • Wednesday 6 April:The paving on the entrance to Budgens car park is getting wider.
  • Thursday 7 April:The blister paving, which delineates the difference between footpath and road, is nearly finished in the entrance road to Budgens Car Park.
  • Friday 8 April:A trench was dug today. It will house the ducting for a new power supply for the War Memorial part of the Manor Waste

To see what happened in week eleven, clickhere

To see what happened in week twelve, clickhere

To see what happened in week thirteen, clickhere

To see what happened in week fourteen, clickhere

To see what happened in week fifteen, clickhere

To see what happened in week sixteen, click here

To see what happened in August, clickhere