Week Five of Manor Waste refurbishment

The schedule for week five includes work on the electrical duct and chambers and cable ducting. Excitingly, we expect La Linia block paving and blister paving to be installed.

For more information about this project clickhere

To see some videos of work in progress clickhere

To see what happened in week one clickhere

To see what happened in week two, clickhere

To see what happened in week three, clickhere

To see what happened in week four, clickhere

  • Monday 22 February: laying of paving blocks started
  • Tuesday 23 February: laying of paving blocks continued
  • Wednesday 24 February: patterns begin to emerge
  • Thursday 25 February: easier access is granted to 30 & 32 High Street
  • Friday 26 February: the main paving at the Dobbins Lane end has been laid

To see what happened in week six, click here

To see what happened in week seven, clickhere

To see what happened in week eight, clickhere

To see what happened in week nine, clickhere

To see what happened in week ten, clickhere

To see what happened in week eleven, clickhere

To see what happened in week twelve, clickhere

To see what happened in week thirteen, clickhere

To see what happened in week fourteen, clickhere

To see what happened in week fifteen, clickhere

To see what happened in week sixteen, clickhere

To see what happened in August, clickhere